Item 15 Passed 11-0

Item 15 — Thursday, May 2, 2024

Official votes

Current official agenda wording

Authorize additional contingency for the construction contract for the St. Elmo Service Center 8 Renovations project with Rodriguez Barr, Inc., d/b/a The Barr Company, AIA, to increase the amount by $66,300, for a revised total amount not to exceed $1,007,632. (Note: This request is for additional contingency only. Participation to date is 6.03% MBE and 8.36% WBE).